ACON Construction Company, Inc. has completed the Sheriff's Office Administration Building - Design/Build Project. CM2133
Substantial Completion was achieved on November 10, 2016; Final Completion on December 10, 2016.
Original Contract $ 7,756,000.00
Change Order $ (987,978.68)
Total Contract Sum $ 6,768,021.32
Work Completed $ 6,768,021.32
Less Previous Payment Applications 1-24 $ 6,429,456.93
Final Release of Retainage/Final Payment $ 338,564.39
Contract Management acknowledges receipt of final leases of lien and consent of Security.
Attachments:
Project Invoice #25 Final
Certificate of Final Completion
Consent of Surety to Final Payment
Final Waiver and Release of Lien Final Payment
All documents can be viewed in Contracts Management Office. |