Rowell Contracting, Inc. has completed the Lift Station No. 1 and No. 3 Replacement Project, CM2301. Substantial completion was achieved on March 2, 2017 and Final completion on June 2, 2017.
Original Contract Sum $ 1,053,000.00
Change Order (No. 1 – 3) $ 34,886.63
Total Contract Sum $ 1,087,886.63
Work Completed $ 1,087,886.63
Less Previous Payment Application 1-4 ( - ) $ 1,033,492.30
Final Release of Retainage/Final Payment $ 54,394.33
Contract Management acknowledges receipt of all final releases of lien and consent of Surety
Attachments:
- Project Invoice #5_Final – Rowell Contracting, Inc.
- Certification of Engineer / Architect, dated July 17, 2017
- Certificate of Substantial Completion, dated March 2, 2017
- Certification of Final Completion, dated June 2, 2017
- Final Waiver and Release of Lien upon Final Payment
- Consent of Surety to Final Payment
|
Release final retainage in the amount of $54,394.33 to Rowell Contracting, Inc., for completion of the Lift Station No. 1 and No. 3 Replacement Project. Funding Source: 71000000-205500 WWLS.
|