Background:

The Summer Beach Development of Regional Impact (DRI) was approved in 1985.  In April 2005, Parcel N-2 was added to the DRI by the 16th amendment to the Development Order (Resolution 2005-75), which also allocated 100 previously approved multi-family residential units to it. 

This proposed change to the Summer Beach DRI Development Order would allow a mix of mix of detached single-family and multi-family (incl. townhomes) residential uses to be constructed on Parcel N-2. No additional units would be added to the DRI, nor would any existing approved units within the DRI be re-allocated to Parcel N-2. The proposed amendment would expand the uses permitted to allow a single-family detached residential product to be constructed in this area.

Request:

Consider NOPC18-003, a Resolution constituting the twentieth amendment to the Development Order for the Summer Beach Development of Regional Impact (DRI); specifically amending the Development Order to a previously approved Development of Regional Impact pursuant to the Notification of a Proposed Change (NOPC) filed by Artisan Homes, LLC, and dated July 25, 2018; providing for development of single-family detached residential units on Parcel N-2; finding that this change does not constitute a substantial deviation from the originally approved DRI Development Oder, as amended; and providing an effective date.

Financial/Economic Impact to Future Years Budgeting Process or Effect on Citizens:
N/A
Action Requested and Recommendation:

Consider NOPC18-003, a Resolution amending the Development Order for the Summer Beach Development of Regional Impact (DRI); specifically amending the Development Order to a previously approved Development Of Regional Impact pursuant to a notification filed by Artisan Homes, LLC; Providing for a mix of detached single-family and multi-family residential uses On Parcel N-2.

Is this action consistent with the Nassau County Comprehensive Land Use Plan?
Yes
Funding Source:
Fee-supported activity

Additional Information Needed for Contracts/Agreements (If Applicable)
Contract Number assigned by Contracts Management:
For non-governmental agencies, has the document been sent to the vendor for signature?
Does the document need to be recorded? If so, who will pay the recordation fee?
Are there any special mailing instructions? (Include contact name, address, deadline for submittal, how to mail such as express mail, FedEx, etc):
How many originals are needed?

ATTACHMENTS:
DescriptionUpload DateType
NOPC18-003 Resolution8/31/2018Resolution Letter
NOPC18-003 Application8/31/2018Backup Material
NOPC18-003 Parcel8/31/2018Backup Material
NOPC18-003 Staff Report8/31/2018Backup Material