APTIM Environmental & Infrastructure Inc. has completed the West Nassau Landfill Flare Station Blower System Replacement. Substantial completion was achieved on October 10, 2016 and Final completion on January 3, 2018.
Original Contract Sum $73,381.00
Change Orders $3,400.00
Total Contract Sum $76,781.00
Less Previous Progress Payment $72,941.95
Balance:
Final Release of Retainage $3,839.05
Attachments:
Application and Certificate for Progress Payment
Project Invoice #397055-RI-00631
Certification of Substantial Completion, dated 10/28/16
Certification of Final Completion dated 1/3/18
Waiver and Release of Lien upon Final Payment from APTIM
Consent of Surety Company to Final Payment |