Florida Infrastructure, Inc. has completed the Bailey/Simmons Road Multi-Use Trail Project (CM2575). Final completion was achieved on September 13, 2019.
Original Contract Sum $1,553,254.73
Change Order (N/A) 9,623.00
Total Contract Sum $1,562,877.73
Work Completed $1,562,877.73
Less Previous Payment Application 1-2 ( - ) $1,406,589.96
Final Release of Retainage/Final Payment $ 156,287.77
Contract Management acknowledges receipt of all final releases of lien and consent of Surety.