BOCC AGENDA ITEM
|
| | | | | | | |
Item Title: | Approval of Fire Rescue 71 Design/ Build Project Change Order #2 and #3 | Date: | 7/13/2020 | Department: | Facilities Maintenance |
|
| | | | | | | | Background: | CM2729 Fire Station 71 Design/Build Project Change Orders approval
Change Order # 2: Reduction of 31,604.00 and the request to extend the Substantial Completion from January 28, 2021 to April 14, 2021.
Change Order #3: Revise the HVAC System to Daikin VRF System and Install DDC Controls with associated installation as listed.
| Request: | Approve and authorize the Chairman to sign the following for Fire Station 71 Design/Build Project, Contract No. CM2729: 1) Change Order # 2- Reduction of 31,604.00 and the request to extend the Substantial Completion from January 28, 2021 to April 14, 2021, 2) Change Order #3- Modify HVAC System at an increased cost of $219,132. | Financial/Economic Impact to Future Years Budgeting Process or Effect on Citizens: | N/A | Action Requested and Recommendation: | Approve and authorize the Chairman to sign the Change Orders for CM2729 Fire Station 71 Design/Build Project
Change Order # 2: Reduction of 31,604.00 and the request to extend the Substantial Completion from January 28, 2021 to April 14, 2021.
Change Order #3: Modify HVAC System at an increased cost of $219,132. | Is this action consistent with the Nassau County Comprehensive Land Use Plan? | NA | Funding Source: | 68223522-562300 - ST71 |
|
| | | | | | | |
Additional Information Needed for Contracts/Agreements (If Applicable) | | Contract Number assigned by Contracts Management: | CM2729 | For non-governmental agencies, has the document been sent to the vendor for signature? | N/A | Does the document need to be recorded? If so, who will pay the recordation fee? | | Are there any special mailing instructions? (Include contact name, address, deadline for submittal, how to mail such as express mail, FedEx, etc): | N/A | How many originals are needed? | One (1) |
|
|