SGS Contracting Services, Inc. has substantially completed construction on the Nassau Amelia Utilities Wastewater Treatment Facility Clarifier Rehab project, Contract No. CM2619. A partial release of retainage in the amount of $40,205 is due to the vendor.
Original Contract Sum: $797,700.00
Net Change Orders: $29,900.00
Contract Sum to Date: $827,600.00
Previous Payments: -$763,895.00
Partial Retainage Due: $40,205.00
After final completion, the remaining final retainage of $23,500 will be presented to the Board at a later date. |