Item Title:Authorize Negotiations with AE Engineering for CEI Services on CR 108 from Middle to US 17 (NC21-032)
Date:5/23/2022
Department:Engineering Services
Background:

Four proposals for Construction Engineering Inspection (CEI) were received on January 12, 2022 in response to RFQ (NC21-032) for the CR108 Safety Improvements from Middle Road to US 17.  The proposals were opened on January 13, 2022.  The evaluation committee met on January 31, 2022 for the purpose of scoring and ranking the proposals for the CEI Services for the project.  Each firm was evaluated by the individual evaluation committee member and then collectively scored and ranked by the full committee.  AE Engineering was the highest-ranking firm, and it is recommended the Board of County Commissioners approve staff to negotiate a contract with AE Engineering for the CEI Services for CR 108 Safety Improvements from Middle Road to US 17.

 

Firm

Total Composite Score

AE Engineering, Inc.

97

CDM Smith

96.8

   
   
   

 

Request:

Approve the evaluation committee’s final ranking of the proposals for Construction Engineering Inspection for the Safety Improvements to CR 108 from Middle Road to US 17 and authorize staff to enter into negotiations with the top ranked firm, AE Engineering, and bring back to the Board for approval and execution.

Financial/Economic Impact to Future Years Budgeting Process or Effect on Citizens:
CEI costs for this project will be reimbursed through an agreement with FDOT.  The improvements to this portion of CR 108 will improve the overall safety of Nassau County residents.
Action Requested and Recommendation:

Approve the evaluation committee’s final ranking of the proposals for Construction Engineering Inspection for the Safety Improvements to CR 108 from Middle Road to US 17 and authorize staff to enter into negotiations with the top ranked firm, AE Engineering, and bring back to the Board for approval and execution.


Is this action consistent with the Nassau County Comprehensive Land Use Plan?
Yes
Funding Source:
Staff will return to the Board of County Commissioners to request approval of a negotiated contract.  The project budget code will be established using FDOT grant money for the Safety Improvements on CR 108 from Middle Road to US 17.

Additional Information Needed for Contracts/Agreements (If Applicable)
Contract Number assigned by Contracts Management:
Contract Number will be assigned at the time the Contract is presented for approval.
For non-governmental agencies, has the document been sent to the vendor for signature?
N/A

Does the document need to be recorded? If so, who will pay the recordation fee?
N/A
Are there any special mailing instructions? (Include contact name, address, deadline for submittal, how to mail such as express mail, FedEx, etc):
N/A
How many originals are needed?
N/A

ATTACHMENTS:
DescriptionUpload DateType
Meeting Notes and Ranking4/25/2022Backup Material